Emergency Bridge Replacement
ConnDOT

Stonington & Groton, CT

Flood waters took out the existing bridge on Route 184, a heavily travelled alternate route to I-95. The replacement bridge is an integrated H-pile—deck—rigid frame construction that required no footings. The concrete in the abutments and deck was placed in one pour and encased the ends of the prestressed beams. The design increased the flow area significantly.

Two first two photos show the setting of the prestressed beam and the third photo shows the existing condition at the start of construction.